Generator Factory Acceptance Testing

All of our generator sets are rigorous prototype tested (FAT) according to ISO-8528 with industrial load banks up to 4MW and protections integrated systems

Testing Process

Visual inspection of the package unit (engine, alternator, control, etc.)

Complete loading and full-load testing 25% -50% - 75% - 100% -110% and with all generator readings recorded on separated period defined according to standards and customers request.

Sudden loads block test to assure generator normal load acceptance with defined limit of voltage drop, frequency drop and recovery time.

Protection Systems

Over/Under Voltage
Over/Under Frequency
Phase failure
Low Oil Pressure
High Coolant Temp.
Low Fuel Level
Over Load
Over Current
Reverse Power
Over/Under Battery voltage
Fail To Start
Charge alternator fail

Loading Test Results

Parameter25%50%75%100%110%Sudd=60%
P (KW)400800120016001760960
IL1 (A)58011681755231025501390
IL2 (A)58511701760232025551390
IL3 (A)58511701760232025551390
VL1L2 (V)400399401400399399
VL2L3 (V)399400400400400400
VL1L3 (V)400400400400400400
Freq. (Hz)505050505050
Speed (RPM)150015001500150015001500
Oil Press. (BAR)3.002.842.782.762.722.80
Engine Temp. (°C)767880818480