Generator Factory Acceptance Testing
All of our generator sets are rigorously tested (FAT) according to ISO-8528 with industrial load banks up to 4MW and integrated protection systems
Testing Process
Visual inspection of the package unit (engine, alternator, control, etc.)
Complete loading and full-load testing at 25% - 50% - 75% - 100% - 110% with all generator readings recorded over a defined period according to standards and customer requirements.
Sudden load block test to ensure generator normal load acceptance within defined limits of voltage drop, frequency drop, and recovery time.
Protection Systems
Over/Under Voltage
Over/Under Frequency
Phase failure
Low Oil Pressure
High Coolant Temp.
Low Fuel Level
Over Load
Over Current
Reverse Power
Over/Under Battery voltage
Fail To Start
Charge alternator fail
Loading Test Results
| Parameter | 25% | 50% | 75% | 100% | 110% | Sudd=60% |
|---|---|---|---|---|---|---|
| P (KW) | 400 | 800 | 1200 | 1600 | 1760 | 960 |
| IL1 (A) | 580 | 1168 | 1755 | 2310 | 2550 | 1390 |
| IL2 (A) | 585 | 1170 | 1760 | 2320 | 2555 | 1390 |
| IL3 (A) | 585 | 1170 | 1760 | 2320 | 2555 | 1390 |
| VL1L2 (V) | 400 | 399 | 401 | 400 | 399 | 399 |
| VL2L3 (V) | 399 | 400 | 400 | 400 | 400 | 400 |
| VL1L3 (V) | 400 | 400 | 400 | 400 | 400 | 400 |
| Freq. (Hz) | 50 | 50 | 50 | 50 | 50 | 50 |
| Speed (RPM) | 1500 | 1500 | 1500 | 1500 | 1500 | 1500 |
| Oil Press. (BAR) | 3.00 | 2.84 | 2.78 | 2.76 | 2.72 | 2.80 |
| Engine Temp. (°C) | 76 | 78 | 80 | 81 | 84 | 80 |